Wet day

No Comments

Weather has definitely not aided work today. The morning saw the second frame being constructed very quickly. However, rain was threatening all morning and then it finally arrived. We had an early lunch before the boys started levelling the second frame into place. Not ideal in the pouring rain.  I decided to leave them to it, as there was nothing I could help with. They continued on battling with the elements to secure the frame in place as more bad weather is forecast for tomorrow and I think they would all have felt happier leaving it fast rather than dangling!!!

We did get the second truss secure as Breezy suggested. Also managed to complete the ridge and put rafters on a third of the building. Some preparation is done ready for tomorrow and there is a tarp over a third of the roof giving an area that we can work under in foul weather. The outlook for tomorrow is not great.

Categories: Autumn 2007, The Project

Big Progress

No Comments

Clive got on site before us and had already started whittling a truss. Security is not really tight with no roof at all and steps that lead up the back over the wall.  It was a beautiful day, almost too hot around lunchtime and all of us guzzling lots of water.

The morning’s challenge was to get one of the trusses up and in place using Clive’s mighty new winch. A very handy new toy!

Clive and Hans had a bit of final touches to the truss framework before it was heave ho into place and it looks great.

That then needed securing by getting some of the ridge beam in and cementing the truss into place. Lots of cement loads for Al and Murray to put on the gable end to make it really start looking like a roof. All the guys are working really hard and achieving loads which is great to see.

Seeing a third of the framework in place was just great.

Chris left today and headed home with a lot less than he arrived with. He has been a HUGE help in all ways. Many, many thanks Chris. Coming back for the “roof party”????

Truss oneTruss one 

Categories: Autumn 2007, The Project

Construction Starts

No Comments

Clive turned up still hung over from Saturday, to be fair he cleared up after the party on Sunday morning and started drinking again celebrating his wedding anniversary and spent the afternoon in bed. I gave him a bottle of water.

Clive finished bashing out holes in the gable wall to accept floor joists while Hans and I finished the middle of the floor and placed poplar boards down to create a platform at 1st floor level. Clive and Hans then started working on the 1st truss.

It is a weird feeling as the building starts to take shape again after spending a week taking it apart.

By the end of the day we had a truss virtually built and the whole of the first floor as a platform to work off. An hour to finish the truss and we should be rocking tomorrow!! 

Categories: Autumn 2007, The Project

Chris Cooked, new Pup

No Comments

A large lie in after a 2.30am finish from the antics the night before. We woke up to the sun shining always lovely.

A few errands in the am and a visit to see Daniella’s new pup a border collie which is adorable. Much needed time for Al and myself at the Bergerie discussing the next steps. It has been a very busy week with very little time to discuss things between ourselves so it was lovely to catch up in the sun on the land. Chris arrived after spending the day with Annie and Murray and we trundled up to see the sculptured limestone and the waterfalls all looking very impressive with the recent snowmelt.

We managed a few beers before Chris cooked some roast chuck for us all.

Categories: Autumn 2007, The Project

Breezys Birthday

No Comments

Took 2 vehicles to St Girons as Chris was keen to be a tourist for the day. Breezy and I had a list of things to do and buy which took slightly longer than anticipated so we missed the market and had to scoff lunch before meeting the guys for half a days work. A productive pm for the lads…with getting a third of the first floor joists in. Clive drilling the holes in the walls and Murray and I  filling in afterwards with stones and cement making it look new!!!  Breezy’s birthday along with Gizelle and Clive’s wedding anniversary plus Martine’s birthday  (married to Johnny, secretary for the mayor) So we had been invited to a “party” partagez which is the equivalent of a “pot luck” in the UK bring something for the meal and something to eat and it is a free for all. Met loads more extremely hospitable and interesting locals who made us all feel very welcome. Chris in his newly purchased beret from the market.

A night to remember!!!!

Categories: Autumn 2007, The Project

Snow

No Comments

The sun finally shone but wow was it cold after the snow getting down to 1200m, a tad parky to say the least.  We had a very successful day today and achieved loads.

Chris collected an extra scaff tower from Murray’s and then  helped Clive to get cement mixer etc on site too.

Clive joined us who is “the man in the know” re the actual structure of the roof and we had been waiting for him before we could progress much further. He is another English chap who  has been in the area for years living just above Couflens in a lovely place which he is gradually doing up along with his wife Gizelle and 3 kids.

By the end of the day the whole roof was stripped off; ridge beam, purlins the lot and a great deal of heave hoing from the guys as the wood was in huge pieces and very wet so doubly heavy.

 

Clive had done a great job at cementing in  the first floor rafters the very large pieces of wood which we had struggled to get up to the Bergerie and it actually feels like progress is being made. Slowly but surely.  7.30pm much needed beers to end a very good day.

Categories: Autumn 2007, The Project

Logs & Pulleys

No Comments

We spoke to Clive the evening before and he said that we would see him at lunchtime after he finished off another job. Hans and I started to shift the large floor beams into the building while Breezy used the mucktruck to collect water from the river and decant it into the 500ltr water but we bought yesterday. The two beams are 7m long and large sections. Each weighs about 750kg. We managed to get then into the building with ropes, pulleys and sweat. With hoists on the safest of the old roof joists we managed to lift the beams into positions where they would be easy to slot into place. After that success we went back to stripping the roof. By the end of the day we were left with a skeleton of a building. Strange to think that if it was in this state when we first saw it we would never have even contemplated buying it. It would have saved us loads of dosh if we had.

Hans' new hatHans' new hat How Big?How Big? HeaveHeave 

Clive did not show in the end so we caught up with him by phone to make arrangements for Friday.

Categories: Autumn 2007, The Project

Solving Problems

No Comments

Very grey day with loads of rain over night and we still need to get the gravel up to behind the barn, not sure if the truck will make it up in the boggy conditions, we will see.

Al loaded 30 sacks of gravel that then Chris tried to get up the hill. In the end it was a mix of truck and muck truck.

We abandoned Murray at the end of the track shovelling the rest of the gravel into sacks for transporting later that day.

 

It was wet and not very safe to get on the roof so Hans went home. Murray had French lessons that afternoon so we were down to Chris, Al and myself.

We decided that time was better spent sorting out the water issue and how to get a regular supply of water at the back of the barn for use for cement. A trip to St Girons and Al and I within 10 minutes had found exactly the right containers to solve the problem…BRILLIANT!!!

Categories: Autumn 2007, The Project

Second Delivery

No Comments

Delivery Day 2 and the truck had arrived at the end of the track before us and had already started unloading masses of materials….and we were just beginning to ponder just how  long shifting all of it was going to take when peep peep Monsieur Le Mayor arrives in full force…luckily on our side, giving the driver what for on why he would not transport the materials up to the Bergerie. He gave it his best shot but to no avail Monsieur Cazale was having none of it and continued unloading!!! At least my concerns re the mayor making life difficult for us were now no more. Phew.

Hans a lovely Dutch chap arrived today to work with us. He has a place just the other side of  Seix and has lots of  experience on roofing so a great asset to the team.

So another day of shifting materials up the track for Chris, Murray and I, while Al and Hans attacked the dismantling of the roof.

Luckily the weather was reasonable which made life a lot easier.

 

End of the day was highly amusing as after many ideas and thoughts re the large wood and how to get it there the end decision was to get Chris’s 4X4 truck with the wood on balanced with the muck truck behind. It looked very funny and I think we all had our doubts if it would actually work but it did at a snails pace it was manoeuvred all the way up to near the front door. This had to be done twice since the wood was so heavy.

Thank goodness we did get it moved that night because with all the rain over night it would not have happened the next day.

Categories: Autumn 2007, The Project

First Delivery

No Comments

Delivery day…will they won’t they drop the materials on the land? I was hopeful but to no avail as Monsieur Cazale was determined that end of the 4X4 track was as far as he was going. Not an ideal start but at least the sun was shining. So Plan B was to use Chris’s 4X4 to transport the materials up to the barn, fairly time consuming but it worked with each round trip taking about 50 mins. Chris was FAB with getting the full truck up the hill. We had managed to shift all of the first load except the large 7.5m pieces of wood by the end of the day which was good as another 17 tonne truck was arriving tomorrow with more materials which would also need shifting. “Muscles Murray” a very tall and strong Scottish chap who we had met before was keen for work so was happy to help us out for the roof. He and Annie have a barn just the other side of Couflens with 10 dogs, 2 horses, some goats and lots of veggies.!!! and plenty of work to do too so any time that Murray can give us is much appreciated. Al and Murray began stripping tin from the roof in the afternoon.